Hi All- We are scheduled to begin blasting on the south end of the site this Thursday [February 27, 2015] at 11:00 am. The process will be similar to the blasting that occurred on the north end of the site over the last few months. The sidewalks at N. Moore Street, N. Lynn Street and Wilson Boulevard will be closed for the 5 minutes leading up to the blast in order to clear pedestrians from the immediate blasting area. Traffic will be stopped on the surrounding streets for 1 minute prior to blasting. This blasting will continue for the next few months; please schedule your plans accordingly if you will be in the area around 11:00am. We thank you all for you cooperation. Best, Emily Duesterhaus, Office Engineer CLARK CONSTRUCTION GROUP, LLC 1735 North Lynn St., Ste 102, Arlington, VA 22209 office. 202.813.1388 cell. 240.278.0651 www.clarkconstruction.com | |||
|