Metro Inspection Report of May 20, 2009
 Login/Join 
posted
Both stations were inspected on May 20, 2009 and all associated
departments have been notified.

Open Issues: Rosslyn:

Mezzanine Level:
New Issues:
5 Lights out on entry escalators

Lower Level Platform:
1 Track Bed light out - COMPLETED
3 Granite Edge lights out - Unresolved (Currently 4 are out)
New Issues:
Elevator #4 Emergency intercom not operating


Upper Level Platform:
2 Lobby ceiling light out (In front of elevator #3) - COMPLETED
New Issues:
Escalator #5 out of service
Escalator #6 used as a walker

Open Issues: Arlington Cemetery:
PID’s blank (towards VA) - COMPLETED
Granite edge lights do not flash - Major repair underway. - Unresolved
Two globes missing - Unresolved
New Issues:
None


Sincerely,
Paul Bumbry
Blue-Orange Line Customer Service Manager
Case # 737603
 