NRCA Collaboration Area
Metro Inspection Report of Dec 28, 2009

This topic can be found at:
https://community.northrosslyn.org/eve/forums/a/tpc/f/6856007081/m/782103345

January 14, 2010, 09:19 PM
Paul Derby
Metro Inspection Report of Dec 28, 2009
Rosslyn and Arlington Cemetery stations were inspected on December 28, 2009 and all associated departments have been contacted. The bike racks were inspected and were in good shape.

Open Issues: Rosslyn:

Mezzanine Level:
2– Escalator side panel lights out (Unit #2) – COMPLETED
1 - Ceiling light out – COMPLETED
3 – Security Camera’s inoperable - Unresolved
New Issues:
1 – PID’s unit blank screen (mounted on wall)
1 – Side Panel light out (against wall beside escalator #1)

Lower Level Platform:
Graffiti on escalator #5 glass - COMPLETED
Debris/trash removal needed (wall lights area) - COMPLETED
1 – Ceiling light out (near escalator #3) - Unresolved
New Issues:
2 – Ceiling lights out (near escalator #6)

Upper Level Platform:
Escalator #5 – Walker (Right handrail not moving) - Unresolved
New Issues:
Escalator #6 – Walker
9 – Track Bed lights out

Open Issues: Arlington Cemetery:
Granite edge lights do not flash - Unresolved
Two globes missing – Unresolved
Pay telephone (7-9602) inoperable - Unresolved
PIDS Track 1- not working - Unresolved
New Issues:
None

Sincerely,

Paul Bumbry
Rail Transportation
Customer Service Manager
Case # 737603